Digitalization of Activities of Support Functions is a MUST for timely delivery of Projects

Every Activity at Construction site need to be systematically mapped and reviewed for effective and efficient working and better results.

In past, I was executing a 2x600 MW thermal power project in West Bengal for Central Government. I was representing a EPC contractor, a blue chip company.

I was Head of Electrical and was inducted from HQ, mid-stream of the project.

Erection activities were on peak and testing had started. I got stuck-up on some issues with a leading electrical package provider (a MNC). They were not sending the testing & rectification support at site. I had taken up the issue with their project manager at Bangalore who apprised me that Payments have not been released for more than one and half years. He had submitted the whole list of pending bills.

I had taken stock of the pending bills with Accounts department and found some outstanding amount in books. I had taken up the matter with higher ups and ensured that such payments are in priority list and were released.

Some more bills were already cleared by Electrical department in past and were pending for a long period for SAP posting after careful scrutiny by Accounts department. When the issue was raised, Bills were cleared by them after constant chase and persuasion. Again I ensured that such payments are in priority list of top management and were released.

Then, I asked the project manager at MNCs Bangalore office for providing field support. Satisfied with some flow of funds from my end, he had arranged the visit of testing engineers to site and I achieved some work in progress. Some systems were commissioned.

But, in such big projects, issues keep on arising. Again, I approached the project manager at MNCs Bangalore office and this time he informed me that he will support when all the pending payments are released.

I observed that a supply bill was pending for the last 3 years and was not traceable in accounts department. We were presuming that its pending for posting on SAP somewhere in pile of bills in accounts department.

Contrary to that, I traced the material in Store’s receipt section at site and found that material is lying in their shelf for the last 3 years and papers either not prepared or not cleared. That’s why material was not sent to stores and was not being reflected in their ledger even.

This material was also required for completion of erection of one the electrical equipment but at a later date.

Immediately, store’s material receipt section had prepared the documents. Material was inspected and cleared and in few days accounts clearance, SAP posting and disbursement were arranged.

MNC had supported the field testing and rectification works, there on and equipment and systems were commissioned.

This small episode, reflects the lack of MIS of different departments/sections and its day to day chase by Project Management team / Construction Management team especially at construction site.

People are mostly busy in identifying bigger issues and their resolve.

Construction support activities are not properly mapped and most of the construction site work is done on manual mode.

Its possible that Construction schedules may change time to time with different paths and approach, but support functions like accounts, material receipt, stores etc., shall be digitized for each and every activity and must be updated on day to day basis with MIS of even pending issues.

Some MNCs have their effective system in force but they also bulged at the peak of site activities. However, Indian companies need a lot of improvement in their working.

Organizations need to strengthen their Organogram and implement them religiously. Especially peak time manpower resources shall be there in place well before the time. Just in time (JIT) concepts are not workable / productive, most of the time, in construction field.

There must be three tier reviews of MIS so that most of the routine type issues are sorted out at tier#1 level and then some at Tier#2 level which may be resolved with senior management level intervention and typical issues are reflected at Tier#3 at top management level.

#casestudy #constructionmanagement #projectmanagement